Local Voices

Metro-North Update

Temporary substations installed by Con Edison are not sufficient to operate full New Haven Line Service.  The reduced power provided by these temporary substations only allows Metro-North to add a limited number of trains through the 8-mile section between Harrison and Mount Vernon, providing approximately 50% of normal service.  As a result, a special schedule is still in effect. See service details at http://bit.ly/S5Cxrf . See Free Emergency Park & Ride info athttp://bit.ly/1bluuBr .


Get more local news delivered straight to your inbox. Sign up for free Patch newsletters and alerts.